Missile Field #2 Site Development Phase III
This work is located on an active missile field site on Fort Greely, Alaska. UNIT was selected to complete the following:
- Site work to include grading, scraping organics, drainage, roads, and fence construction.
- Constructing underground utilities to include a utilidor water system, communication duct banks, and hemp shielded medium voltage electrical duct banks.
- Install perimeter fences, security lighting, and an electronic security system which will include CCTVs and acoustical fencing .
- This also includes furnishing and installing power conductors to Missile Field 2 from the vicinity of the power plant.